PQC laying at NH-28...
BRIEF AND DETAILED SPECIFICATIONS OF PAVEMENT QUALITY CONCRETE (PQC)
PURPOSE:-
・ The purpose of this Quality Plan for Construction of Pavement Quality Concrete (PQC) is to provide detailed Construction Methodology, Materials used, Resources deployed.
SCOPE:-
・ The Scope of this Segmental Quality Plan/ Methodology shall covers the construction of pavement quality concrete insertion of dowel bars, tie bars in accordance with the requirement of Technical Specifications and in conformity with the line, grades and cross sections shown in drawings.
It covers the following activities:
DEFINITIONS:-
The words like contract, Contractors, Engineer (Synonymous to Engineer's representative), Drawing, Employer, Government, Works, Worksite used in this Quality Plan shall be considered to have the meaning as understood from the definitions pertaining Quality Management System Developed for the Particular Project.
The following abbreviation shall have the meaning as set forth below:
CROSS REFERENCE:-
This Segment Quality Plan should be read in conjunction with the following documents:
RESPONSIBILITY:-
S.
NO
|
Activity Description
|
Performing
|
Checking/
Verifying
|
Approving
|
01
|
Preparation Quality Plan
|
Section-in� charge &
QC Engineer
|
Works
Manager &
QC Manager
|
Project
manager
|
02
|
Selection and Testing of various materials for PQC, Mix Design & Trials etc prior to start of activity
|
Section-in- charge & QC Engineer
|
Works Manager & QC Manager
|
Project manger
|
03
|
Survey, setting out fixing of string lines prior to start of PQC
|
Surveyor
|
Section-in-charge / Site Engineer
|
Engineer
|
04
|
PQC Paver deployment at various locations and other logistics management etc.
|
Section-in-charge / Site Engineer
|
Works Manager
|
Project
Manager
|
05
|
Batching & Mixing of concrete as per approved Design mix
|
Batching Plant �in-charge
|
QC Engineer / Lab technician
| |
06
|
Control of movement of Paver and maintenance 0checks / control during operation
|
Paver engineer / Supervisor
|
Paver- in � charge
|
Project Mechanical Engineer for effective control of Paving operation
|
07
|
Transportation, Placing, Compaction and finishing of PQC layers,
|
Section-in- charge / Site Engineer
|
QC Engineer / Lab technician
|
Engineer
|
08
|
Texturing, curing Joint Cutting and Sealing operations for PQC
|
Section-in-charge / Site Engineer
|
QC Engineer / Lab technician
|
Engineer
|
09
|
Inspection & Testing of PQC as per approved ITP and maintaining all formats.
|
QC Engineer / Lab Technician
|
QC Manager / QC Engineer
|
Engineer
|
PROCEDURE:-
The detailed Construction Methodology involved in execution of PQC including Quality Assurance & Control etc. has been described in the following sub-chapters.
Survey and Setting out for PQC:
The following steps are involved in Setting out of string wire before lying
PQC:
Center line of Carriageway will be marked at every 50M intervals on DLC surface by using Total station.
Approval of survey and setting will be ensured and survey check sheet CGGC 34 17 01 is filled prior to commencement of the laying activity.
Material Required:
Cement:
(i) Ordinary Portland Cement IS: 269
(ii) Portland Slag Cement IS: 455
(iii) Portland Pozzolana Cement IS:1489
Cement to be used may preferably be obtained in bulk form. It shall be stored in accordance with stipulations contained in Clause 1014 and shall be subjected to acceptance test prior to its immediate use.
.
Coarse Aggregate:
Fine Aggregate:
Clean, natural sand from River Banas form location Triveni 20km form Ladpura will be used. The material conforming IS: 383 is ensured.
The fine aggregate shall consist of clean, natural sand or crushed stone sand or a combination of the two and shall conform to IS: 383. Fine aggregate shall be free from soft particles, clay, shale, loam, cemented particles, mica, organic and other foreign matter. The fine aggregate shall comply with MoRTH 602.2.4.3.(Fourth Revision : August 2001).
(The grading limits for all in aggregates shall be per IS:383 for 20mm nominal size Aggregate for Pavement Quality Concrete )
Sieve Designation
|
Percentage passing the Sieve by Weight
|
40 mm
|
100
|
20 mm
|
95 � 100
|
4.75 mm
|
30 � 50
|
600 micron
|
10 � 35
|
150 micron
|
0 � 6
|
Water:
456: 2000.
In case of PQC During hot weather, water for preparation of concrete will be taken form water chilling plant.
Admixtures:
Admixture conforming to IS: 6925 and IS: 9103 to improve workability of concrete or extension of setting time to be done.
Storage of materials :
Aggregates:
Aggregate will be stock piled separately and sufficient distance will be maintained from each fraction to avoid intermingling.
Cement
Bulk cement will be stored in bulk storage containers having 200MT capacity and the number of such bulkers will be sufficient to cater to the requirement at site.
Water
Water will be tanks covered at top and cleaned at regular intervals. The intake of pipe will be enclosed to exclude silt and other solid materials and there shall be a minimum depth of 0.60 m of water below the intake at all times.
Proportioning of concrete
Concrete Strength
The pavement concrete should be a class M-40 concrete with a minimum 28 days compressive characteristic strength of 40 MPa
1. Characteristic flexural strength at 28 days = 4.5 MPa
2. Target mean strength at 28 days = 5.80MPa
3. Water cement ratio =0.45 Maximum
4. Slump as per IS: 1199 =31+/-15 mm
7days (avg.)
28 days (avg.)
(Flexural strength of any Six consecutive 7day test result) >4.50+1.65*s
S: Standard deviation of the group.
Workability:
Separation Membrane :
First coat will be applied immediately after DLC laying and compaction and the other before start of PQC.
Preparation of base :
Surface will be made clean of dirt or extraneous material and free from damage before application compound.
Joints:
Concrete Penetrometer and testing as per ASTM C 403 will be used in monitoring setting of concrete / Maturity of concrete and saw cutting period.
Initial saw cut of 3mm wide , 100mm depth in transverse and longitudinal direction will be provided after initial set(approximately 6~8hrs).
Final saw cutting 10~12mm wide ,20~25mm depth will de provided after 14days of curing at accommodate joint sealant.
Transverse joints:
Contraction joints will be provided at every 4.5m interval except where expansion joints are provided.
Transverse joints to be provided at the junction of the approach slabs of bridged and the rigid pavement and special location e.g. transition sections i.e. transition of flexible vs. rigid pavement.
Expansion joints will be provided at the junction of the approach slabs of Bridges and the rigid pavement.
Contraction Joint:
Expansion Joints:
Joint filler board for Expansion joint will be premoulded joint filler as per MoRTH spec. 602.2.7
Premoulded joint filler conforming As per IS: 1838 or BS: 2630
The filler for each joint shall be furnished in a single piece for the full depth and width required for the joint.
Holes to accommodate dowel bars will be as accurately board or punched to give a sliding till on the dowel bars.
Joints will be provided at the junctions of rigid and flexible pavement with transition slab as per the drawings.
Where due to unavoidable conditions (for example:- joints at two contract package) joint are to be provided, dowel bars are fixed into the rigid pavement.
Transverse construction joint
Longitudinal joints
Dowel bars
These shall confirm to the requirements of IS: 432, IS: 1139 and IS: 1786 as relevant. The dowel bars shall confirm to Grade S 240 and tie bars to Grade S 415 of I.S.
It should be mild steel round, free from dirt, loose rust, scale straight and burring restricting slippage in the concrete.
Dowel bars shall be covered by a thin plastic sheath for at least 2/3 of length from one end for dowel bars in Contraction joint or half the length plus 50mm for expansion joints.
For Expansion joints, a closely fitting cap 100mm long cotton waste placed over sheathened end of each dowel bar.
Tie bars
It should be perpendicular to the line of the joint, with the center of each bar on the intended line of the joint within a tolerance of + 50mm and with a minimum cover of 30 mm below joint groove.
Weather and Seasonal Limitations:
Concreting during monsoon months:
Concreting in Hot Weather:
Care will be taken in reducing temperature of concrete such as use of
Chilled water, sprinkling of chilled water over aggregates.
Guide wires
Use of guidewires
Each guidewire shall be at a constant height above and parallel to the required edges of the slab as described in the contract / drawing within a vertical tolerance of + 3 mm.
The guidewires shall be supported and stakes preferably not more then 8 m apart by connectors capable of fine horizontal and vertical adjustment.
The stack shall be positioned and the connectors maintained at their correct height and alignment before commencement of work.
Care will be taken to avoid any disturbance to the guidewire during paving by any construction equipment or any other means.
CONSTRUCTION:-
10.1 Concrete production, transportation, Paving, Texturing and Curing:-
Dumpers having hydraulic jack system to unload having capacity 35 Mt (Approx. 9 cum) concrete will be deploy for transportation of concrete.
The slip from-paving machine shall compact the concrete by internal vibration and shape it between the side forms with a conforming plate and oscillating finishing beams.
The final finish of the surface will be done by super smoother attached to the rear portion of the Paver.
Manson Trolley will be placed in between Paver and Texturing and Curing Mechine (TCM) for rectification of any surface defects.
The alignment of the Paver shall be controlled automatically from the guide wire by 4 set of level sensors and 2 set of steering sensors attached to the Paver.
The surface of concrete slab will Tine-textured in a direction parallel to the longitudinal axis of the carriageway.
Texturing / Tining will be done with a specified machine specially designed for the purpose for providing grooves at a uniform spacing of 18 mm to 21mm.
・ Depth = 3mm to 4mm
・ Width = 3mm
After providing initial cut entire PQC will be covered with Hessian cloth and water turned for 14 days.
Trail length:
The Trial length will be constructed at least one month advance before starting of concrete paving work.
Trial length of 60mm with same width, Depth etc as per permanent work will be done at nearer to site.
Transverse joints and longitudinal joint of each type that are to be included in the pavement work will be constructed and assessed in the Trial length.
Density:
11.2 Strength:
Minimum of thirty (30) beams for flexural strength and thirty cubes for compressive strength will be prepared form the concrete delivered to the paving plant.
The mix will be designed to achieve
§ The average flexural strength >4.5 +1.65*s(Mpa)
[s=standard deviation]
§ Strength of any sample >fck � 1.65 s
§ The average compressive strength of the cores ≥ 0.8/ (Average compressive strength of the thirty cubes.)
Temperature Measurement:
The temperature development in the concrete slab should be recorded after every 3 hours during hardening after installment of the thermometer & temperature-age relationship should be determined.
It should be measured in the middle of the slab (vertically) at a horizontal distance of at least 1000 mm from any free end.
Inspection Dowel Bars:
Alignment of dowel bars and construction joint shall be checked by measurement relative to guide wires.
The position of dowel bars, filler board will be measured after carefully exposing plastic concrete across the whole width of concrete.
Preparation of joint and sealing of joint grooves:
All grooves shall be cleaned of any dirt or loose material by air blasting with filtered, oil-free compressed air.
Before sealing the temporary seal provide for blocking the ingress of dirt, soil etc., shall be removed.
A height compressible heat resistant paper-backed debonding strip as per drawing shall be inserted in the groove.
In the case of longitudinal joints, heat resistant tapes may be inserted to block the leakage though bottom of the joint.
Sealing with sealants:-
Priming and sealing with applied sealants should not be carried out when temperature in the joint groove to be sealed is below 7 deg C.
If hot applied elastomeric type sealant complying AASHTO M282 is used it shall be heated and applied from a thermostatically controlled, indirectly heated preferably with oil jacketed melter and pourer having recirculation pump and extruder (This is applied at junction of Asphalt and concrete pavements.
Cold applied polyurethane / Polysulphide type complying BS: 5212-1990Sealan will be mixed and applied according to the time limit specified the Manufacture to the concrete pavements.
Care such as temperature and time of sealing will be emphasized to avoid any bulge of sealant during contraction of joint.
The type and details of different joints treatment are tabulated below:-
TYPE OF JOINT
|
JOINT
DETAILS & TREATMENT
| |||||
Polysulphide
Sealant(cold)
|
Debonding
Strip
|
3~4
Mm
Groove
|
Soft
Rope
|
Butt
Joint
|
Compressible
Filler Board
| |
Longitudinal
| ||||||
Expansion
| ||||||
Construction
| ||||||
Contraction
| ||||||
Testing of applied Sealant:-
Joint sealant compound and primer should be tested in:
In case if deliveries are made more frequent than testing may be reduced to every three months.
Measurement of texture depth � Sand Patch Method
The surface texture will be measured as per the method laid down in MoRTH601.12.1 and the same is recorded in lab format.
Opening to Traffic:-
No vehicular traffic including contractor's vehicles will be allowed on the finished surface until a field flexural strength of minimum 4.50 MPa has been achieved where the average flexural strength of minimum 3 specimens should exceed 4.50+1.65 s(s=standard deviation).
Each series of test specimens for measurement of flexural strength should consist of minimum 3 test specimens.
Prior to the opening to traffic the joints should be sealed and areas adjacent to the pavement should be completed to a degree that will ensure traffic safety.
Quality Assurance and Control Checks
As part of Quality Assurance this Segment Quality Plan for PQC has been prepared in line with the specification provided in relevant MoRTH clauses, Contract Supplementary Technical Specification and other Codes/ Standard / Specifications etc. elsewhere mentioned in this Plan.
As a part of Quality Control all the Inspection and Testing requirements for various activities involved in the laying of PQC will be carried out as per relevant MoRTH Specifications & Contract Technical Specification etc. As described in Inspection and Test Plans attached to this Segment Quality Plan for PQC.
These Inspection and Test Plans shall consist of the type of Inspection and name of the Test to be conducted for Product Realization, the frequency of testing acceptance criteria and category of Inspection.
Inspection and Test Plans should be revised whenever there any change in methodology and specifications etc.
Nonconformities in PQC:-
Any Non-Conformity observed during field Inspection and also during Testing of Materials / mixes / laying system etc. the same should be recorded in the specified Nonconformance Report and necessary Corrective / Preventive actions should be initiated to prevent such things in future.
QA/QC Engineers are responsible to control the Nonconforming products as described in Procedure, and relevant section-in-charge site engineers are to take appropriate corrective /preventive actions.
All Product Non-Conformities shall be observed, recorded, corrective/preventive actions and closing of NCR's should be as per the established documented procedure described in Project Quality Plan.
Safety & Environmental Requirements:
Hazard Identification, Risk assessment and Risk control measures for each activities and sub-activities involved in the present Segment shall be identified and necessary action plan shall be initiated.
Environmental Aspects and Impacts associated with various activities and sub-activities involved in the present segment and their mitigation/control measures shall be identified and necessary measures shall be initiated.
SEQUENTIAL OPERATION OF PQC LAYING
![]() |
DLC layer Approval
|
The survey, Setting out, fixing of String line
|
Clearance to B/Plant for Production of concrete after checking string line & Equipment.
|
![]() |
Transportation of Mix to Site
|
YES
SEQUENTIAL OPERATION OF PQC LAYING
![]() |
|

|
![]() |
YES
Rectification of surface defects (if any) manually by Mesons.
|
Texturing & curing by TCM and Test rate of spraying.
|
Fixing of Stopper after End of Day's Work.
|
Initial Joint cutting after the setting of concrete
|
Cleaning of joint and fixing backup rod.
|
SEQUENTIAL OPERATION OF PQC LAYING
![]() |
Covering PQC with hessian cloth and water curing for min.14 days.
|
Removal of hessian cloth and final joint cutting
|
Cleaning of joint and providing soft rope, debonding strip, polysulphide sealant, compressible filler board, butt joint as mentioned in Table-2 in PQC methodology
|
Test texture depth by Sand Patch Method
|