Water proofing membrane laying


Application of Polyprime.

Block Work Quality

As a QC Engineer during site visit I do observed these kind of non-conformance many time the root cause analysis is too difficult for me, all the masons are trained procedure briefing has been given to them in their speaking language I came to the conclusion its lack of skilled mason, I will escalate my findings to construction team we need experienced masons.
Cavity Wall tie not provided in alternate layer.
Fair face of block not provided at door.
Block not stacked properly.
Lines and Level not monitor properly.
Block not fixed properly and top layer placed.
Stretcher Bond not followed at junction.
Mortar thickness not within tolerance.
Block not placed properly at junction.
Manual cut block used resulting uneven mortar joints.
Curing in block-work not monitored.
Line and Level of joint not monitor properly.




Block Work

As a QC engineer during the site visit following Non-Conformance observed in block work and issued to the site team now site team need to close out the nonconformance's prior to further work at the locations.

Which involves the physical rectification of block-wall along with document confirming that a training has been provided to the masons and the same issue will not be repeated in future.

When multiple minors NCR issued for the same issue then this can be considered a "systemic failure." it will affect the reputation of the subcontractor which can terminate their contract with us.

1. Cavity wall tie not provided as per specification

2. Joints are not uniform and are not properly filled.

3. Scrabbling not done properly at the column.
1. Cavity wall tie not provided as per specification
2. Joints are not uniform & are not properly filled.
3. Lines are not leveled properly.
4. Scrabbling not done properly at the column.
1. Plaster Metal Lath to be fixed all around the joint.
1. Curing of lintel not being monitored.

2. Mortar for block work to be kept properly and out of direct sunlight to reduce water loss.

3. Block to be stored properly to avoid damage.

Prior to Backfilling

Back-filling around the structure is going to start, as a QC Engineer I will send the following comments to site team and ask for their actions prior to backfilling.
1. Tie rod holes to be filled.
2. The structure below ground level to be protected.(C-4 Paint and Polyethylene sheet)
3. Waste concrete, Binding Wire, Nails, Wooden Ply, Polythene etc to be removed.
Tie rod holes to be filled and structure to be protected.
Waste concrete, Binding Wire, Nails, Wooden Ply, Polythene etc to be removed.
The structure below ground level to be protected.(C-4 Paint and Polyethylene sheet).
The structure below ground level to be protected.(C-4 Paint and Polyethylene sheet).
The structure below ground level to be protected.(C-4 Paint and Polyethylene sheet).

Surface Preparation


Why site engineer's don't include surface preparation in their activity?

Preparation for Light weight concrete work is going on in checklist items surface preparation always get ignored
site team will be notified to rectify following comments prior to screeding.
Tie rod holes to be filled.
Defect in concrete to be repaired.
Tie rod holes to be filled.
Debris to be removed.
Parapet columns to be casted prior to screed.

Muscat Rain



Heavy rain in muscat..never seen muscat like this....its terrific ...